Record 27INR0434
Screen signal presentLyra Solar
- Filed entity
- Juno Solar 4
- Nameplate
- 500 MW
- County
- Borden
- Point of interconnection
- 345 kV Muleshoe (#59922)
- Interconnection agreement
- July 1, 2025
- FS + NTP field
- Yes
- Claimed COD
- September 15, 2027
Sample · ERCOT Project Claim Check
Can an evaluator treat the 1,000 MW Lyra solar-plus-storage pair at Muleshoe as equally advanced?
Public-record answer: No.Executive read
Both records are 500 MW, list Borden County, and connect at the 345 kV Muleshoe point of interconnection. Both show signed interconnection-agreement dates. Only the solar record displays the combined financial-security and notice-to-proceed signal in the July 2026 filing.
A model, memo, or seller statement that treats the pair as one uniformly advanced 1,000 MW complex is not supported by this filing.
Record 27INR0434
Screen signal presentRecord 26INR0636
Screen signal absentClaim test
The filing lists distinct INR numbers and filed entities. Both records name Muleshoe 345 kV as the point of interconnection.
The records do not carry the same public commitment signal. The storage record claims an earlier COD while its combined FS + NTP field remains “No.”
Names and POI suggest a relationship, but this filing does not establish parent ownership, financing, construction status, or whether the records share a coordinated build plan.
Source and boundary
Source: ERCOT GIS Report, July 2026, parsed August 27, 2026. Values above reproduce the public filing fields used by Firm Power Research.
Boundary: This sample tests what one public filing supports. It is not engineering, legal, investment, ownership, construction, deliverability, congestion, or completion-probability analysis. “FS + NTP” reproduces a combined source field; it does not reveal which component may be absent when the value is “No.”
Apply this to your decision
We will show what the ERCOT filing confirms, what it contradicts, and which questions should move into deeper diligence.
Request a Project Claim Check